San Francisco Ferry Terminal October
Construction Progress:
» Guardrail
installation near Sinbad’s restaurant and walkway delineation (with yellow
truncated domes) will be completed in the south terminal area.
» Installation of the
architectural finish detailing, such as the ornamental rail and lighting around
the perimeter of the deck, and the portal construction (including steel
framework and granite panels with stainless steel roofing and canopy) will be
underway.
» Offshore, in the
"southern basin area," the piles will be driven for the breakwater
which will protect the south terminal berthing area. (The north terminal is
already protected by the existing structures).
» Construction of the
float and ramps continues off site in Sacramento. We will anticipate floating
(no pun intended) them down the Sacramento River when they are complete (south
float in November, north in December).