|
Vallejo
waterfront |
The Big Shake-up
At 5:04 p.m. on Tuesday,
October 17, 1989 …
with over 62,000 fans filling Candlestick Park for the third
game of the World Series, and commute traffic in full swing,
suddenly it struck: the 7.1 magnitude earthquake that was later
called "Loma Prieta". Fires erupted in the Marina District
of San Francisco. A double-decker freeway collapsed in West Oakland.
And one segment of the upper deck on the east span of the Bay Bridge
collapsed onto the lower level, putting the bridge totally out of
service.
The Bay Bridge was out of
commission for several nearly a months as Caltrans mounted an
emergency restoration program. The thousands and thousands ofMore
than 80,000 commuters from East Bay cities that normally took the
bridge to San Francisco had to find alternative transportation. BART
played a major role in solving the transportation crisis, and
Vallejo responded by dramatically increasing its newBartLink bus
service along I-80 to BART’s El Cerrito Del Norte Station in El
Cerrito.
The earthquake clearly
showed that the alternative for trans-bay transportation was the
ferry, and suddenly the importance of having high-speed ferry
service on the bay became apparent to everyone. Belchamber says,
"We had an ideaknew that ferry service could be bigger than it
was, but until the earthquake, there was never an opportunity to
demonstrate it." " So with funding from Caltrans,
excursion and tour boats were pressed into emergency ferry service
between Richmond, Berkeley, Alameda, and other East Bay points to
get commuters to and from San Francisco.
So, with funding from
Caltrans, excursion and tour boats were pressed into ferry service
in Richmond, Berkeley, Alameda and other East Bay points to get
commuters to and from San Francisco. In Vallejo,
Within a week after the
quake, two high-speed catamaransthree boats — two 25-knot
mono-hulls and one catamaran — were loaned borrowed from
Washington State Ferries and put into operation between Vallejo and
San Francisco. After the reopening of the Bay Bridge in
mid-November, Vallejo to San Francisco ferries retained the greatest
proportion of ridership of any other emergency ferry service.
By January 1990, with the
Bay Bridge restored, some ferry commuters went backreturned to their
automobiles. , However, but others had discovered the pleasures of
"taking a ferry to work" and stayed with their new-foundnewly
found transportation. Some of the new ferry services across the Bay
survived,survived, and someunfortunately most did not.
In Vallejo, with Caltrans
funding at an end, the twothe three ferries on loan were returned to
their home in Washington State. The fAlthough the demand for ferry
service had dropped somewhat after the reopening of the bridge, it
still remained high, and it was obvious that Vallejo had to make a
move.
Finding Funding
Other significant events
occurred at about this same time. The first was the 1990 passage of
State Proposition Proposition #116 in June 1990, the
"California Air Quality & Transportation Improvement
Act" ("CATIA"), a $2 billion measure that which
included $10-million capital earmarked for the purchase of equipment
for Vallejo’s ferry system.
With capital funding and
operating expenses in hand, Vallejo was about to enter the transit
business.
"That’s when I
entered the picture!" said Pam Belchamber, a transportation
analyst for the city at the time.According to Belchamber, "We
As a result of the Loma Prieta quake, we moved rapidly and obtained
the Metropolitan Transportation’s (MTC) approval of funding for a
$240,000 study of improved ferry service from Vallejo and other
locations in the Bay Area." Between November 1990 and November
1991, the "Regional and Vallejo Ferry Plan" was developed
by the City of Vallejo and MTC. Also during 1991, a proposal to
Congress was made for a special "earmark" of
transportation funds for the Vallejo ferry system.
Vallejo hired Pacific
Transit Management (PTM) to write the Vallejo Ferry Plan. The PTM
team included Art Anderson Associates, a naval architectural firm
whose staff included Marty Robbins, now Vallejo’s Marine Services
Manager responsible for overseeing Baylink operations and the ferry
capital program.
In November 1991, the
Vallejo City Council approved the Vallejo Ferry Plan, which provided
a clear vision of where we wanted to go with our ferry service. The
program called for buying two 35-knot ferryboats, setting our own
schedules, and contracting with an experienced ferry operator.
Based on that plan, the MTC
committed additional federal operating funds for Vallejo’s transit
system. In December 1991, President George Bush (senior) signed the
landmark Intermodal Surface Transportation Efficiency Act (ISTEA),
which, through the advocacy and hard work of Congressman George
Miller, included an allocation of $17 million for the "North
Bay Ferry Demonstration Program," e.g., the Vallejo ferry
project.
Belchamber continued,
"Early in 1992, we quickly began the environmental review and
funding application process with the Federal Transit Administration
(FTA), which we finished in June and then submitted to MTC and the
FTA for approval.
"But, as with many
major projects, we encountered a few bumps in the road. A local
group, ‘Citizens for a Natural Waterfront’ sued the City in
August, insisting on a full environmental impact report (EIR) for
the ferry project. The funding application process went forward
despite the lawsuit." In August 1993, the environmental lawsuit
was rejected by the Solano County Superior Court, but Citizens for a
Natural Waterfront appealed the decision to the California State
Court of Appeals, which was later rejected in mid-1994.
"Later that spring, Red
& White Fleet informed us that a vessel would not be available
to continue San Francisco to Vallejo service after June 1994, unless
the city separately funded extensive repairs to the M/V Catamaran.
After Red & White Fleet’s announcement, it made more sense to
us to obtain an interim replacement/backup vessel. We also decided
to place the Vallejo-San Francisco service out to competitive bid
after Red & White Fleet indicated that they needed substantially
higher subsidies than we had been paying.
"Based on our Request
for Proposals, we purchased the "M/V Jet Cat Express" (a
28-knot catamaran) from Catalina Express of Long Beach in spring
1994. We also selected Blue & Gold Fleet to provide Vallejo’s
ferry service, which began with the Jet Cat on July 1, 1994.
CONTINUE